Ongoing Projects

IF YOU HAD DONE ANYTHING THAT IS NEEDED TO BE DONE IN THE PLAN, PLEASE EDIT ANYTHING THAT HAVE BEEN CHANGED BEFORE TO SHOW THE CURRENT PROGRESS.

Wolvhaven Metro Mechburg Extension Project

Project name: WolvHaven Metro Phase 2: East Mechanicsburg Extension

Players who are currently responsible for the project: chickenjoshbwak (Head Architect)

Company(s): Fried Transportation - Temaqix Holdings

Line 1 Extension Project

Line 1

Introduction: Metro Line 1, the oldest metro line in WolvHaven will be extended from its current Northern Terminus, La Resistance, to Mechanicsburg station via underground tunnels. Mechanicsburg, a station situated in Northwest Mechanicsburg, will be the brand new terminus for Metro Line 1.

La Resistance (1)(2)(10) -<>- Northgate (1)(7) -<>- Mechanicsburg (1)(6)(8) >>>> Mechanicsburg Depot


Project Section Code (P=Plan D=Design C=Construction T=Technical Edits) Project Section Name Percentage of Completion (Approximate Value) Status of Completion
P1 Planning of tunnel route
100%
COMPLETED
D1 Finalization of station layouts
100%
COMPLETED
D2 Finalization of station designs
100%
COMPLETED
C1 Tunnel burrowing
100%
COMPLETED
C2 Construction of La Resistance M1 station platforms
100%
COMPLETED
C3 Construction of Northgate M1 station platforms
100%
COMPLETED
C4 Construction of Mechanicsburg M1 station platforms
90%
INCOMPLETED
C5 Tunnel Link to Mechanicsburg Depot
100%
COMPLETED
T1 Implementation of Metro+ Card Readers
0%
INCOMPLETED
T2 Implementation of train spawning mechanism
100%
COMPLETED
T3 Implementation of signage
100%
COMPLETED


Any aspiring FTRANS Partners wanting to propose any sorts of designs or have any queries shall do so in the Temaqix Holdings discord, specifically in the #ftrans channel at https://discord.gg/BjyDC7Y.:

Line 4 Extension Project

Line 4 Metro Line 4 will be extended from Dakota Interchange, will continue North and stop at Ditchill and York stations with trains pulling into the East River Depot, bringing an end to service.

Dakota (2)(4) -<>- East river (4)(7) -<>- York (4)(6)(7)(8) >>>> East River Depot

Project Section Code (P=Plan D=Design C=Construction T=Technical Edits) Project Section Name Percentage of Completion (Approximate Value) Status of Completion
P1 Planning of tunnel route
100%
COMPLETED
D1 Finalization of station layouts
60%
INCOMPLETED
D2 Finalization of station designs
20%
INCOMPLETED
C1 Tunnel burrowing
5%
INCOMPLETED
C2 Construction of Dakota M4 station platforms
100%
COMPLETED
C3 Construction of Ditchill M4 station platforms
100%
COMPLETED
C4 Construction of York M4 station platforms
60%
INCOMPLETED
C5 Tunnel Link to East River Depot
0%
INCOMPLETED
T1 Implementation of Metro+ Card Readers
0%
INCOMPLETED
T2 Implementation of train spawning mechanism at Depot
0%
INCOMPLETED
T3 Implementation of signage
5%
INCOMPLETED


Extra Info : M4's terminus platform will be on the top platform, with trains heading to City Hall will be the one at the bottom.

Any aspiring FTRANS Partners wanting to propose any sorts of designs or have any queries shall do so in the Temaqix Holdings discord, specifically in the #ftrans channel at https://discord.gg/BjyDC7Y.:

Line6/8 Extension Project

Line 6/8

Hillview (6) -<>- Bohill (6) -<>- York (4)(6)(7)(8) >>>> East River Depot

Project Section Code (P=Plan D=Design C=Construction T=Technical Edits) Project Section Name Percentage of Completion (Approximate Value) Status of Completion
P1 Planning of tunnel route
100%
COMPLETE
D1 Finalization of station layouts
100%
COMPLETE
D2 Finalization of station designs
100%
COMPLETE
C1 Tunnel burrowing
100%
COMPLETE
C2 Construction of Hillview M6 station platforms
100%
COMPLETE
C3 Construction of Bohill M6 station platforms
100%
COMPLETE
C4 Construction of York M6 and M8 station platforms
100%
COMPLETE
C5 Tunnel Link to East River Depot
100%
COMPLETE
T1 Implementation of Metro+ Card Readers
100%
COMPLETE
T2 Implementation of train spawning mechanism
100%
COMPLETE
T3 Implementation of signage
70%
INCOMPLETE


Any aspiring FTRANS Partners wanting to propose any sorts of designs or have any queries shall do so in the Temasaac Holdings discord, specifically in the #ftrans channel at https://discord.gg/BjyDC7Y.:

Line 7 Extension Project

Line 7

Primerose(3)(6)(7)(8) -<>- Sillonner (7) -<>- Highgate (1)(7) -<>- Ditchill (4)(7) -<>- York (4)(6)(7)(8) >>>> East River Depot

Planning of tunnel/viaduct route : INCOMPLETE Finalization of station layouts : INCOMPLETE Finalization of station designs : INCOMPLETE Tunnel burrowing : COMPLETE Construction of Sillonner M7 station platforms : COMPLETE Construction of Highgate M7 station platforms : INCOMPLETE Construction of Ditchill M7 station platforms : INCOMPLETE Construction of York M7 station platforms : INCOMPLETE Implementation of Metro+ Card Readers : INCOMPLETE Tunnel link to East River Depot : INCOMPLETE Implementation of train spawning mechanism @ Depot : INCOMPLETE Implementation of signage : INCOMPLETE

Info : We are uncertain how Line 7 will go from Highgate to Depot.

Any aspiring FTRANS Partners wanting to propose any sorts of designs or have any queries shall do so in the Temaqix Holdings discord, specifically in the #ftrans channel at https://discord.gg/BjyDC7Y.:



North South Expressway(NSE)& CIE Extension Project

Project name: North South Expressway (From Stadium to York) and CIE extension to Mechanicsburg

Players who are currently responsible for the project: minebuilder1223, GukkyGukz

Project Section Code (P=Plan D=Design C=Construction T=Technical Edits) Project Section Name Percentage of Completion (Approximate Value) Status of Completion
P1 Planning of expressway viaducts and interchange
100%
COMPLETED
D1 Finalization of Interchange layouts
100%
COMPLETED
D2 Finalization of viaduct designs
100%
COMPLETED
C1 Construction of NSE main viaducts
100%
COMPLETED
C2 Construction of CIE main tunnels
100%
COMPLETED
C3 Construction of the NSE and CIE interchange
100%
COMPLETED
C4 Construction of Streets around the interchange
90%
INCOMPLETED
C5 Interchange decorations and greenery
100%
COMPLETED
T2 Road markings
100%
COMPLETED
T3 Implementation of signage
100%
COMPLETED

Plan:Mechberg Interchange plan.jpg

Info: The NSE will extend to Central and East Mechanicsberg and connect with CIE with a huge interchange in the middle. the CIE tunnel have reached to the ground and the construction of the interchange are currently ongoing.

If you have any questions about the plan and construction feel free to make a sentence below: